DSCM Evaluation Plan

Process

Each DSCM finalist has a Primary Evaluator assigned from the OpenSolaris I-team:
  • Bazaar, v 0.7, Stephen Hahn
  • GIT, v 1.2.2, Frank van der Linden
  • Mercurial, v 0.8, Mike Kupfer

NOTE: GIT v 1.2.4 was initially the finalist. But problems with local repository support in both v 1.2.4 and 1.2.3 caused us to revert to v 1.2.2.

Packages containing the candidates are available on the SCM downloads page. The Primary Evaluator is not performing a full quantitative evaluation. Rather, the Primary Evaluator is:
  • understanding how the tools work in detail,
  • testing typical operations and operations known to often cause problems,
  • evaluating the source code to determine whether it is well-constructed and suited for ongoing use and improvement in the OpenSolaris environment.
The Primary Evaluator will submit a report to the tools-discuss mail list detailing the evaluation results. Additional reports from community members are welcome and encouraged. Reports (see the Evaluation Form) should be sent to the tools-discuss mail list by the deadline (see Schedule below). The Primary Evaluator will roll up this input as part of his report.

Schedule

Weeks 1 & 2
  • Evaluation and draft report by Primary Evaluator.
  • Draft report sent out at the end of Week 2.
Week 3
  • Primary Evaluator gets feedback on draft report and works through input/questions sent in during the first two weeks.
  • Community input due by the end of Week 3.
Week 4
  • Final report generated that includes findings, assessment, community input and information about implementation costs.
Tentative Dates
  • Week 1 START = 3/20/06 END = 3/24/06
  • Week 2 START = 3/27/06 END = 3/31/06
  • Week 3 START = 4/03/06 END = 4/07/06
  • Week 4 START = 4/10/06 END = 4/14/06